DevelopmentNMC

LIC Square Fly-over Hurdles Cleared: District Administration Issues Award for Land Acquisition

The path to the completion of the much-anticipated flyover near LIC Square has been cleared, thanks to the District Administration’s recent move. The unresolved land acquisition issues had placed the flyover project in limbo. Now, with the necessary land acquired, the construction can finally proceed, promising relief to the daily commuters and businesses affected by the delay.

The Importance of the LIC Square Flyover

A Vital Infrastructure Project

The LIC Square flyover is a critical infrastructure project designed to ease the traffic congestion in the area. This 5.6 km long flyover, starting from Automotive Square, descends near LIC Square, providing a direct route that bypasses several traffic-heavy intersections.

Historical Delays

Despite the importance of this project, construction had stalled due to unresolved land acquisition issues. While the segment of the flyover up to Naidu Hospital was completed, the stretch between Naidu Hospital and LIC Square remained untouched. This delay has caused significant inconvenience to the local populace.

The Role of the District Administration

Award Issued for Land Acquisition

District Collector Dr. Vipin Itankar played a pivotal role in resolving the land acquisition issues. His office issued an award for the acquisition of 2,700 square meters of land, affecting 17 properties. The estimated compensation for this land acquisition stands at Rs 40 crore.

Compensation and Next Steps

The compensation amount will be disbursed to the affected property owners in the coming days. This move has paved the way for the final phase of construction, with officials from the Maharashtra Metro Rail Corporation Limited (MMRCL) assuring that the remaining ramp work will be completed within two-and-a-half months.

Construction Details

Engineering Specifications

The flyover boasts impressive engineering specifications. The maximum height of the flyover is 11.5 meters, while the minimum height is 5.5 meters. The ramp leading up to LIC Square will be 200 meters long and 19 meters wide, ensuring a smooth flow of traffic beneath it.

Progress and Completion Timeline

According to Maha Metro, more than 80% of the flyover’s construction is already complete. Once the land is handed over, the final segment of the project will be finished within 70 days, bringing much-needed relief to commuters.

Impact on Local Traffic and Businesses

Current Traffic Challenges

Currently, the area around Kasturchand Park and RBI Square has turned into a traffic mess due to the incomplete flyover. The road stretch beyond RBI Square is blocked, causing significant detours and traffic jams.

Business Disruptions

The pending construction work has severely affected local businesses. Shops, schools, hospitals, and even a prominent Gurudwara have been suffering due to the prolonged delays. Some business owners have called for compensation to cover the losses incurred.

Future Traffic Management

Once the flyover is complete, the roads around Kasturchand Park will need to manage traffic from multiple flyovers, including the Katol Road flyover, Automotive flyover, and the Kingsway Y-shaped flyover. Effective traffic management will be crucial to avoid future congestion.

Community Response and Expectations

Public Sentiment

The delay in construction has caused frustration among the citizens. The traffic jams and detours have disrupted daily routines, leading to widespread discontent. However, the recent progress has rekindled hope for a smoother commute.

Business Owners’ Perspective

Local business owners have been vocal about the financial strain caused by the delay. Many are relieved that the project is finally moving forward, but they also seek compensation for the losses they’ve endured over the years.

The clearance of land acquisition hurdles marks a significant milestone in the LIC Square flyover project. With the District Administration’s proactive approach and Maha Metro’s commitment, the final phase of construction is set to proceed swiftly. This development promises to alleviate traffic woes, benefit local businesses, and enhance the overall infrastructure of the area.

1. What caused the delay in the LIC Square flyover construction?

The primary reason for the delay was the unresolved land acquisition issues between Naidu Hospital and LIC Square.

2. How long is the LIC Square flyover?

The flyover spans 5.6 kilometers, starting from Automotive Square and descending near LIC Square.

3. What is the compensation amount for the land acquisition?

The estimated compensation amount for the land acquisition is Rs 40 crore.

4. When will the remaining construction be completed?

The remaining construction is expected to be completed within 70 days once the land is handed over to Maha Metro.

5. How will the completion of the flyover benefit the local community?

The completion of the flyover will ease traffic congestion, improve commute times, and provide relief to local businesses affected by the delays.

Nagpur Updates

Nagpurupdates is your local/Digital news, entertainment, Events, foodies & tech website. We provide you with the happening news, Page3 Contain and all about Nagpur Foodies & Infrastructure from the Nagpur and world.

Related Articles

Leave a Reply

Your email address will not be published. Required fields are marked *

Back to top button
Ads Blocker Image Powered by Code Help Pro

Ads Blocker Detected!!!

We have detected that you are using extensions to block ads. Please support us by disabling these ads blocker.

Powered By
Best Wordpress Adblock Detecting Plugin | CHP Adblock

Adblock Detected

Disable Your Add Block To View Page.