Ambazari Bridge to Open for Public on April 1: Govt to HC

The long-awaited opening of the Ambazari Bridge in Nagpur has been officially announced. According to an affidavit presented in the Nagpur Bench of the Bombay High Court, the bridge will be fully operational for public use starting April 1, 2025. This announcement follows years of construction delays, bureaucratic hurdles, and public inconvenience. The Public Works Department (PWD) and Maharashtra State Electricity Transmission Company Limited (MSETCL) have assured the completion of all pending works by March 31, 2025.


Project Background and Timeline

Why Was the Bridge Delayed?

The construction of the Ambazari Bridge faced repeated delays due to multiple factors, including:

  • Shifting of 132KV High-Tension Cables – A crucial factor in the delay was the relocation of these power lines.
  • Lack of Timely Funds – The government had not sanctioned the necessary budget on time.
  • Bureaucratic Approvals – Coordination between multiple agencies led to unnecessary lags.

Court’s Intervention

The Nagpur Bench of Bombay HC took note of the persistent delays and issued strong directives to expedite the project. The court emphasized that prolonged construction was leading to severe traffic congestion near the Vivekananda Memorial at Ambazari Lake, creating daily challenges for commuters.


Breakthrough Decisions and Final Steps

Government’s Commitment to Completion

After continuous pressure from the High Court, the state government finally sanctioned ₹3.77 crore for the relocation of high-tension cables. These funds were directed to MSETCL, allowing them to complete the relocation process without further hindrance.

Key Meetings and Progress Reports

A high-power committee meeting was held on February 10, 2025, under the leadership of Additional Divisional Commissioner Madhavi Khode Chaware. In this meeting, the officials from PWD, MSETCL, the Irrigation Department, and the Nagpur Municipal Corporation (NMC) reviewed the project status and committed to an April 1 deadline.


Impact on Traffic and Commuters

Traffic Congestion Challenges

The delay in opening the Ambazari Bridge led to:

  • Increased congestion on alternative routes
  • Longer travel times for daily commuters
  • Unsafe conditions for pedestrians

Expected Relief After Opening

With the full opening of the bridge, commuters can expect:

  • Smoother traffic flow
  • Reduced travel time
  • Improved safety for vehicles and pedestrians

Structural Enhancements and Flood Control Measures

Flood Mitigation Efforts

The Central Water and Power Research Station (CWPRS) conducted an independent study that ruled out the Swami Vivekananda statue as a cause of flash floods in Nagpur. Instead, their report pointed out that limited passage beneath the old bridge was a primary reason for water overflow during heavy rains.

To prevent future flooding, authorities have introduced:

  • Enhanced water drainage mechanisms
  • Improved flood mitigation barriers

Strengthening of the Ambazari Dam

The Irrigation Department confirmed that 95% of dam-strengthening work is completed, with the remaining work set to finish by March 31.


Lessons Learned and Future Infrastructure Plans

Avoiding Future Delays

One of the key takeaways from this project is the importance of inter-departmental coordination. The high-power committee has recommended:

  • Better project oversight to ensure future timelines are met
  • Proactive problem-solving measures to avoid bureaucratic roadblocks
  • Regular updates to the public on large-scale projects

Upcoming Infrastructure Projects in Nagpur

With the successful completion of Ambazari Bridge, the government aims to focus on:

  • Upgrading road networks to support the increasing population
  • Expanding flyovers to reduce congestion in high-traffic areas
  • Improving public transport connectivity

After years of delays, the much-needed Ambazari Bridge will finally open to the public on April 1, 2025. The project faced multiple obstacles, from fund shortages to bureaucratic hurdles, but judicial intervention and public pressure ensured its completion. Commuters can now look forward to smoother travel and reduced congestion in the area. Moving forward, it is crucial for authorities to learn from these delays and implement better planning strategies to prevent similar setbacks in future projects.


1. When will the Ambazari Bridge open?

The bridge will be fully open for public use on April 1, 2025.

2. Why was the bridge construction delayed?

The project faced delays due to funding issues, bureaucratic approvals, and the relocation of high-tension power cables.

3. How will the bridge impact traffic in Nagpur?

Once open, the bridge will reduce congestion, cut down travel time, and improve road safety in the area.

4. What measures were taken to prevent flooding near the bridge?

The CWPRS study identified water drainage issues, leading to the construction of flood mitigation barriers to prevent future flooding.

5. What lessons have been learned from this project?

The project highlighted the importance of timely funding, better inter-departmental coordination, and proactive problem-solving to prevent unnecessary delays.

Nagpur Updates

Nagpurupdates is your local/Digital news, entertainment, Events, foodies & tech website. We provide you with the happening news, Page3 Contain and all about Nagpur Foodies & Infrastructure from the Nagpur and world.

Related Articles

Leave a Reply

Your email address will not be published. Required fields are marked *

Back to top button

Adblock Detected

Disable Your Add Block To View Page.