RTO Flyover Nears Completion, Expected to Open by June 1

RTO Flyover Nagpur : The long-awaited RTO Flyover in Nagpur, aimed at easing traffic congestion on Amravati Road, is finally in its last phase of construction. The Public Works Department (PWD), which is overseeing the project, expects completion by May 31, despite facing challenges such as land acquisition and bridge reconstruction. Once opened, the flyover will significantly improve traffic movement in one of the city’s busiest corridors.
Project Overview
Why is the RTO Flyover Important?
- Reduces Traffic Congestion: The flyover will provide seamless movement of vehicles, reducing bottlenecks.
- Improves Connectivity: Links key areas including University Campus Square and Bole Petrol Pump Square.
- Enhances Safety: Eliminates chaotic intersections and minimizes accident risks.
Project Cost and Scope
- Total Length: 2.85 km
- Cost: Rs 245 crore
- Part of ARTIP: An initiative under the Amravati Road Traffic Improvement Project (ARTIP)
- Executing Body: National Highway (NH) Division of PWD
Construction Progress and Challenges
Current Construction Status
As per PWD officials, approximately 90% of construction is complete. The flyover structure is nearly finished, with just a few critical areas pending completion.
Key Milestones Achieved
✅ Flyover slab completed, except for Ravi Nagar Square. ✅ Law College Square girders placed and ready for traffic. ✅ Ultra High-Performance Fiber Reinforced Concrete (UHPFRC) used to avoid pillars at major junctions. ✅ New bridge construction near RTO underway.
Remaining Work
❌ Slab completion over Ravi Nagar Square (Expected in 20 days). ❌ Reconstruction of old Ravi Nagar bridge (To begin in 10 days). ❌ Land acquisition near RTO for RE Wall. ❌ Approval for tree-cutting permits.
Technology Used in Construction
What is Ultra High-Performance Fiber Reinforced Concrete (UHPFRC)?
The PWD has employed cutting-edge Malaysian technology (UHPFRC) to construct key portions of the flyover without placing pillars at major intersections. This enhances durability and minimizes disruptions at Ravi Nagar Square and Law College Square.
Challenges Delaying Completion
Land Acquisition Issues
One of the primary roadblocks has been the delayed approval for land acquisition near RTO, crucial for constructing the flyover’s RE Wall.
Delays in Tree Cutting Permissions
- The Nagpur Municipal Corporation (NMC) has requested objections before granting tree-cutting approvals.
- PWD planted 5,100 trees as compensation, yet approvals remain stalled.
Bridge Reconstruction Delays
- The bridge near RTO, which is over 50 years old, is being rebuilt to accommodate the flyover.
- Another bridge at Ravi Nagar Square is set for demolition and reconstruction, causing further road closures.
Expected Traffic Impact During Final Phase
- Law College Square to Bole Petrol Pump remains closed due to ongoing bridge work.
- Traffic diversions will continue until at least one side of the bridge is completed.
- PWD aims to minimize disruptions, but some inconvenience is unavoidable until full completion.
Public Reactions and Expectations
Residents and daily commuters have mixed feelings about the project. While most welcome the infrastructure upgrade, many have expressed frustration over the delays. Local businesses along Amravati Road have reported a decline in foot traffic due to prolonged construction activities.
Government’s Response and Future Plans
Officials have assured that all pending approvals will be expedited. Additional road improvements, including footpath development and resurfacing, will be undertaken post-flyover completion.
The RTO Flyover project is a game-changer for Nagpur’s traffic management. Despite facing obstacles, its completion by May 31, 2025, is expected to bring much-needed relief to thousands of commuters. Once operational, it will enhance connectivity, reduce congestion, and ensure safer road conditions.
1. What is the current status of the RTO Flyover construction?
The flyover is 90% complete, with final touches including the slab over Ravi Nagar Square and bridge reconstruction pending.
2. When will the RTO Flyover officially open?
The PWD expects to complete construction by May 31, 2025, with an official opening anticipated by June 1, 2025.
3. Why is the RTO Flyover important for Nagpur?
The flyover aims to decongest Amravati Road, improve traffic flow, and enhance overall road safety for commuters.
4. What challenges have delayed the project?
Delays in land acquisition, tree-cutting permits, and bridge reconstruction have extended the project timeline.
5. Will there be further road closures due to construction?
Yes, certain road sections will remain closed, and traffic diversions will be in place until the work is fully completed.