DevelopmentNagpur Local

Butibori Flyover Under Inspection: NHAI Mulls Partial Opening Today

Nagpur, Butibori Flyover Collapse Update: What happens when a vital piece of infrastructure falters unexpectedly? This very question loomed over Nagpur on Tuesday morning when the 1.69-km-long Butibori flyover suffered a structural failure. Constructed by the National Highways Authority of India (NHAI) at a cost of Rs70 crore, this flyover, designed to ease congestion at the bustling Butibori Industrial Area intersection, witnessed the collapse of a section. The collapse was triggered by a heavy puller vehicle carrying a transformer, leaving the city grappling with chaos and unanswered questions.

The Incident Unfolds

The collapse occurred around 9:30 AM on Tuesday, shaking the confidence in what was considered a modern engineering marvel. A cantilever section caved in by a few inches, exposing iron bars and damaging multiple support beams. This left one lane completely barricaded and traffic diverted to the service roads below. For commuters, industrial units, and emergency services, the day quickly turned into a logistical nightmare.


Immediate Response and Inspection (Butibori Flyover Collapse Update)

Expert Team Steps In

By Wednesday, an expert team comprising NHAI officials, VNIT (Nagpur) professors, and the bridge’s original designers swung into action. Their primary aim? To investigate the root cause of the collapse. Samples from the damaged sections were collected for a thorough analysis to assess structural integrity.

Initial Observations

Team observations included cracks in section joints and uneven patches at several spots. Exposed iron bars and crumbling concrete pointed to potential weaknesses in construction or maintenance. Nets were swiftly installed under damaged sections to prevent further debris from falling, while traffic police (Nagpur) worked tirelessly to manage the resulting congestion.


Possible Causes of Collapse

Overloading: A Major Suspect

While the heavy load carried by the transformer vehicle is a primary suspect, officials are hesitant to pin the blame solely on it. “Excessive load could be one reason, but we are exploring all possibilities,” stated an NHAI official.

Structural Flaws

Could there have been oversight during construction or proof-checking? The involvement of VNIT professors and IIT Bombay during the initial design phase suggests otherwise, but no hypothesis is being ruled out.

Weathering and Maintenance

Nagpur’s climate and the stress of heavy traffic might have taken a toll. Was regular maintenance conducted, or were there lapses? Only a detailed report will clarify.


Current Safety Measures

Barricades and Diversions

To ensure commuter safety, one lane beneath the flyover has been barricaded. This diversion has unfortunately led to heavy congestion on alternate routes, affecting daily commuters and emergency services.

Repair Timeline

The contractor responsible for the flyover has been tasked with grouting the damaged sections. While repairs are expected to take at least a month, NHAI is exploring the possibility of reopening unaffected sections to ease traffic.


Impact on Commuters and Businesses

Traffic Chaos

Motorists traveling towards Wardha, Chandrapur, and Hyderabad are bearing the brunt of the closure. Crawling traffic has become the norm, with even ambulances struggling to navigate through.

Economic Repercussions

Local businesses and industries in the Butibori area have reported delays in transportation, impacting productivity and supply chains.


Future Steps by NHAI

Partial Opening Plans

NHAI officials have hinted at reopening the flyover partially by Thursday afternoon. However, this will only happen after an interim safety assessment ensures no further risks.

Comprehensive Investigation

With experts from VNIT and IIT Bombay involved, the investigation aims to deliver conclusive findings soon. These results will shape repair strategies and ensure such incidents don’t recur.


The Butibori flyover collapse is a wake-up call for infrastructure planning and maintenance in India. While immediate measures are being taken to address the crisis, the incident underscores the importance of rigorous quality checks and proactive maintenance. As Nagpur’s residents await the reopening of this vital route, lessons from this incident must pave the way for safer, more reliable infrastructure across the nation.


1. What caused the Butibori flyover collapse?

The exact cause is still under investigation, but overloading and potential structural flaws are being examined.

2. When will the flyover be fully operational?

Repairs are expected to take at least a month, though partial reopening may happen soon.

3. How is traffic being managed?

Traffic has been diverted to service roads, causing significant congestion. Efforts are underway to streamline movement.

4. Who is responsible for the repairs?

The contractor who constructed the flyover has been directed to carry out the repair works under NHAI’s supervision.

5. What safety measures are in place?

Barricades, nets under damaged sections, and detailed inspections are being conducted to ensure commuter safety.

Nagpur Updates

Nagpurupdates is your local/Digital news, entertainment, Events, foodies & tech website. We provide you with the happening news, Page3 Contain and all about Nagpur Foodies & Infrastructure from the Nagpur and world.

Related Articles

Leave a Reply

Your email address will not be published. Required fields are marked *

Back to top button

Adblock Detected

Disable Your Add Block To View Page.