Runway Recarpeting at Nagpur’s Dr. Babasaheb Ambedkar International Airport to be Completed by May 2025: MIHAN Informs HC
Nagpur Airport runway recarpeting: The long-awaited runway recarpeting project at Dr. Babasaheb Ambedkar International Airport in Nagpur is finally nearing its end. MIHAN (Maharashtra Airport Development Company), which operates the airport in collaboration with the Airports Authority of India (AAI), has confirmed that the work is set to be completed by May 21, 2025. This announcement was made through an affidavit submitted by Abid Ruhi, Senior Airport Director of MIHAN, in response to a Public Interest Litigation (PIL) before the Nagpur Bench of the Bombay High Court.
Background of the Runway Recarpeting Project
Why the Recarpeting is Necessary
The runway at Dr. Babasaheb Ambedkar International Airport has been showing significant signs of wear and tear due to daily operations. The surface has deteriorated to the point where loose gravel and rough patches pose potential risks during aircraft landings and take-offs. The last recarpeting was carried out a decade ago, making this maintenance work crucial to ensure the safety and efficiency of the airport.
Initial Delays and Challenges
The recarpeting work, which was initially planned for an earlier date, faced several delays. These delays were primarily due to bureaucratic hurdles, logistical challenges, and the complex nature of the work required. The project, essential for the smooth functioning of the airport, has been a point of concern for both passengers and airlines.
Current Status and Future Timeline
Confirmation of Completion Date
According to the affidavit submitted by MIHAN, the contractor responsible for the runway recarpeting has been finalized through a tender process by the AAI. A detailed project schedule has been provided, with a clear commitment to completing the work by May 21, 2025. This timeline is now set in stone following the issuance of the work order on May 14, 2024.
Steps Taken to Mitigate Disruption
To minimize the disruption caused by the runway closure, MIHAN has been proactive in coordinating with airlines. All airlines operating from the airport were informed in December 2023 about the upcoming closures, allowing them ample time to reschedule flights and adjust operations accordingly.
Implications for Passengers and Airlines
Impact on Flight Schedules
The ongoing runway work has inevitably led to adjustments in flight schedules. Some flights have been rescheduled or rerouted to ensure passenger safety and avoid operational conflicts. While this has caused some inconvenience, the timely communication by MIHAN has helped in reducing the impact on travelers.
Safety Measures During the Recarpeting Process
Safety remains the top priority during the recarpeting process. The airport has implemented stringent measures to ensure that ongoing operations do not compromise the safety of passengers or aircraft. Temporary closures of the runway are being managed meticulously to align with the project’s progress.
Technical Aspects of the Recarpeting
Materials and Techniques Used
The recarpeting involves the use of high-grade materials designed to withstand heavy aircraft traffic and harsh weather conditions. Advanced techniques are being employed to ensure that the new surface is durable and can support the airport’s operations for the next decade or more.
Environmental Considerations
In addition to safety and durability, the recarpeting project also considers environmental impacts. Efforts are being made to reduce the carbon footprint of the construction work, including the use of sustainable materials and methods.
The Role of MIHAN and AAI in the Project
MIHAN’s Responsibility and Oversight
MIHAN, as the operating body of the airport, holds the primary responsibility for overseeing the recarpeting project. Their role includes managing the project’s progress, coordinating with contractors, and ensuring compliance with safety standards.
Collaboration with AAI
The Airports Authority of India (AAI) has played a crucial role in facilitating the recarpeting project. From finalizing the contractor to ensuring that the project adheres to national and international aviation standards, AAI’s involvement has been instrumental in moving the project forward.
Legal and Public Scrutiny
PIL and High Court’s Involvement
The delay in the recarpeting project led to the filing of a Public Interest Litigation (PIL) before the Nagpur Bench of the Bombay High Court. The court’s scrutiny ensured that MIHAN and AAI were held accountable for the delays and that a clear timeline was established.
MIHAN’s Response to Public Concerns
In response to the concerns raised by the public and the court, MIHAN has been transparent about the challenges faced during the project. The affidavit submitted by Abid Ruhi detailed the steps being taken to complete the project and mitigate any further delays.
Future Prospects for Dr. Babasaheb Ambedkar International Airport
Post-Recarpeting Benefits
Once the recarpeting is complete, the airport is expected to see significant improvements in its operational efficiency. The new runway surface will not only enhance safety but also enable the airport to handle more traffic, thereby boosting its capacity and services.
Long-Term Maintenance Plans
MIHAN has also outlined long-term maintenance plans to ensure that the runway remains in optimal condition. Regular inspections and timely repairs will be part of the ongoing strategy to prevent future degradation.
The completion of the runway recarpeting at Dr. Babasaheb Ambedkar International Airport marks a significant milestone in ensuring the safety and efficiency of one of Nagpur’s key infrastructure assets. While the delays have caused some inconvenience, the steps taken by MIHAN and AAI demonstrate a strong commitment to delivering a high-quality, durable runway that will serve the region for years to come. As the May 2025 deadline approaches, passengers and airlines can look forward to smoother, safer operations at the airport.
1. Why was the runway recarpeting at Nagpur Airport delayed?
The delays were due to a combination of bureaucratic challenges, logistical issues, and the complexity of the work involved.
2. When will the runway recarpeting be completed?
The recarpeting is scheduled to be completed by May 21, 2025.
3. How will the recarpeting affect flight schedules?
Some flights may be rescheduled or rerouted to minimize disruption during the recarpeting process.
4. What materials are being used for the recarpeting?
High-grade, durable materials that can withstand heavy aircraft traffic and harsh weather conditions are being used.
5. How is passenger safety being ensured during the recarpeting?
Stringent safety measures and temporary runway closures are being managed to align with the progress of the recarpeting project.