RTO Flyover in Final Stage; Slab Work at Ravi Nagar to Begin Soon

The long-awaited RTO Flyover is finally nearing completion, with the final slab work at Ravi Nagar Square set to commence soon. The National Highway (NH) division of the state Public Works Department (PWD), responsible for the project, has confirmed that preparations for laying the slab using Ultra High Performance Fibre Reinforced Concrete (UHPFRC), also known as Malaysian Technology, are complete.
A Major Step Towards Completion
Slab Work at Ravi Nagar: The Last Piece of the Puzzle
PWD officials have stated that this is a critical phase of the project. “It is a complex process, but we have made the necessary preparations. Once the slab at Ravi Nagar is laid, the flyover structure will be fully completed,” said a senior PWD official.
What Happens Next?
After the slab work is done, the final construction activities include:
- Building a retaining wall near RTO
- Replacing the existing 50-year-old bridge
- Completing minor roadworks below the flyover
Project Overview: A Long-Awaited Infrastructure Boost
The RTO Flyover is a 2.85 km long structure, stretching from University Campus Square to just before Bhole Petrol Pump Square on Amravati Road. The total project cost is estimated at ₹245 crore. It is part of the ₹478 crore Amravati Road Traffic Improvement Project (ARTIP), aimed at easing congestion in one of Nagpur’s busiest corridors.
Sister Project: Wadi Flyover
The RTO Flyover was planned in conjunction with the Wadi Flyover under ARTIP. Both flyovers are crucial to the city’s traffic decongestion strategy, implemented under the guidance of the Ministry of Road Transport and Highways (MoRTH).
Challenges Faced: Delays and Roadblocks
Despite significant progress, the flyover’s completion has been delayed due to multiple challenges:
1. Missed Deadlines
Initially slated for opening on February 28, the project encountered several roadblocks, pushing the completion date to May-end. However, additional work such as footpath construction and roadworks will extend the full project completion timeline to July.
2. Tree-Cutting Permissions
One of the biggest hurdles has been obtaining tree-cutting approvals from the Nagpur Municipal Corporation (NMC). Out of the required 127 trees, permission has been granted for only 82 trees so far. The delay in obtaining clearance has significantly impacted the construction timeline.
3. Land Acquisition Challenges
Another major roadblock has been acquiring the necessary land. PWD officials have highlighted the delays in acquiring essential plots, leading to cost overruns and contractor compensation claims.
4. Public Money at Stake
Project delays translate to increased costs, impacting taxpayers. Contractors claim compensation for project slowdowns, leading to additional expenses for the government.
Upcoming Developments
Once the slab work at Ravi Nagar is completed, the PWD will move on to reconstructing another decades-old bridge near Ravi Nagar, estimated at ₹1 crore.
Infrastructure Improvements After Completion
Upon completion, the flyover is expected to bring significant improvements, including:
- Reduced Traffic Congestion: A smoother traffic flow along Amravati Road.
- Shorter Travel Times: Faster commute between key locations.
- Enhanced Safety: Reduced road accidents and pedestrian risks.
- Improved Connectivity: A seamless link between major city areas.
The RTO Flyover is set to transform Nagpur’s traffic system. While challenges such as tree-cutting approvals and land acquisition have delayed the project, the final stages are now underway. Once completed, the flyover will significantly reduce congestion and provide commuters with a smoother and safer travel experience.
1. When will the RTO Flyover be completed?
The flyover is expected to open by May-end, with additional work continuing until July.
2. What is the total cost of the RTO Flyover project?
The project is estimated at ₹245 crore, as part of the ₹478 crore Amravati Road Traffic Improvement Project (ARTIP).
3. What technology is being used for the slab work?
The slab work is being completed using Ultra High Performance Fibre Reinforced Concrete (UHPFRC), also known as Malaysian Technology.
4. Why has the project been delayed?
The primary reasons include land acquisition challenges, tree-cutting permission delays, and contractor claims.
5. How will the flyover benefit commuters?
It will significantly reduce congestion, shorten travel times, and enhance road safety for motorists and pedestrians.